Deane Public Works in association with their DLJ Joint Venture partners Jacopa have delivered this outstanding project on behalf of NI Water.

project details

Contract Value: £680k
Project Duration: 6 Months (Complete Dec 2021)
Client: RNLI
Client Consultant Engineer: RPS Group
Main Contractor: Woodvale Construction

Company Profile

Download our company profile to see of our services and how we work.

COMPANY PROFILE

Let’s Start Work
Together

To discuss your project feel free to contact us. We will get back to you with 1-2 business days or just call us now.

About Project

The works were phased around the existing treatment works and included the temporary works to phase out the old plant to the new RBC plant. The new treatment works upgrade will meet environmental regulations for a population projection of +25years.

Deane Public Works in association with their DLJ Joint Venture partners Jacopa have delivered this outstanding project on behalf of NI Water.

The Tamlaght Wastewater Treatment Works (Originally built in 1988) is located just off the Belfast Road outside Tamlaght, Co. Fermanagh, approximately 4 miles south-east of Enniskillen. The final effluent flows into a tributary of Upper Lough Erne.

Upgrade works include: New Inlet Works, Copasac Chamber, Storm Tank, 2 Packaged RBC units, EMS Pumping Station and New MCC Kiosk to deliver a fully compliant works to serve the Tamlaght WwTW catchment for the existing and predicted future population.